Volunteers inside a new home in progress.
6126 Melrose Drive

Family: Felicia Otey
House Leader:Bill Giardini
Sponsors: Keller Williams and Randolph High School

DATEDAYACTIVITY
Feb 28Thurs.Clean and level crawl space
Mar 3-7Mon-FriBuild Floor System (on site) Cut lumber & mark plates (at warehouse)
Mar. 8Sat.Build walls (warehouse) & deliver to site
Mar. 12Wed.Group from Lexington KY from 8:30-4PM
Mar. 15 - Mar. 22Sat. to Sat.Erect walls and trusses apply blueboard to walls deck roof install windows ext. doors hurricane clips and deadwood
Mar 25, 27, 29Tues. Thurs. Sat.Install porch beams barge rafters facia attic access & floor plumbing electrical HVAC rough-in
Apr 1, 3, 5Tues. Thurs. Sat.Install wall and floor insulation (Sheet rock by sub) vinyl siding
Apr 8, 10, 12Tues. Thurs. Sat.Paint walls build porches finish vinyl siding and shutters
Apr 15, 17, 19Tues. Thurs. Sat.Begin landscaping install underlayment floor covering
Apr 22, 24, 26Tues. Thurs. Sat.Install & paint interior doors and trim install cabinets plumbing and electrical
Apr 29 May 1, 3Tues. Thurs. Sat.Install closet hardware window blinds storm doors bathroom accessories touch up paint landscape
May 6, 8, 10Tues. Thurs. Sat.Work pinch list blow attic insulation.