| DATE | DAY | ACTIVITY |
|---|---|---|
| 2/21/08 | Th | Footings and block work (contract) Clean crawl space Cut wood and mark wall plates |
| 2/23/08 | Sa | Build Walls in warehouse |
| 2/26/08 | Tu | Install sub-floor;deliver walls Prepare trusses |
| 2/28/08 | Th | Install sub-floor;deliver walls Prepare trusses |
| 3/1/08 | Sa | Wall-raising Ceremony Erect walls and trusses; start sheathing walls |
| 3/4/08 | Tu | Install pull-down stairs and attic storage install porch header Erect storage shed |
| 3/6/08 | Th | Install pull-down stairs and attic storage install porch header Erect storage shed |
| 3/8/08 | Sa | Deck roof and apply felt Finish sheathing and wrap Install hurricane clips and blocking |
| 3/11/08 | Tu | Drip edge and facia; Start electrical rough in;plumbing HVAC rough-in (contract) |
| 3/13/08 | Th | Drip edge and facia; Start electrical rough in;plumbing HVAC rough-in (contract) |
| 3/15/08 | Sa | Shingle roof; install door and windows and baffles; finish electrical rough in |
| 3/18/08 | Tu | Finish inspections and insulate walls Start Sheet-rock (contract) |
| 3/20/08 | Th | Finish inspections and insulate walls Start Sheet-rock (contract) |
| 3/22/08 | Sa | Easter weekend; no work |
| 3/25/08 | Tu | Finish sheet-rock; start porches Prep for siding |
| 3/27/08 | Th | Finish sheet-rock; start porches Prep for siding |
| 3/29/08 | Sa | Start siding-porches; Paint walls |
| 4/1/08 | Tu | Start siding-porches; Paint walls |
| 4/3/08 | Th | Start siding-porches; Paint walls |
| 4/5/08 | Sa | Floor tile; finish siding and porches |
| 4/8/08 | Tu | Floor tile; finish siding and porches |
| 4/10/08 | Th | Floor tile; finish siding and porches |
| 4/12/08 | Sa | Install kitchen cabinets and countertips; doors and baseboards install electrical fixtures |
| 4/15/08 | Tu | Install kitchen cabinets and countertips; doors and baseboards install electrical fixtures |
| 4/17/08 | Th | Install kitchen cabinets and countertips; doors and baseboards install electrical fixtures |
| 4/19/08 | Sa | Paint Trim and doors Start Landscaping |
| 4/22/08 | Tu | Paint Trim and doors Start Landscaping |
| 4/24/08 | Th | Paint Trim and doors Start Landscaping |
| 4/26/08 | Sa | Finish Landscaping; Install blinds and shelves; clean and wax floors |
| 4/29/08 | Tu | Finish Landscaping; Install blinds and shelves; clean and wax floors |
| 5/1/08 | Th | Finish Landscaping; Install blinds and shelves; clean and wax floors |
| 5/10/08 | Sa | Finish needed work Landscape back up Dedication |