Family: Hattie Smith
House Leader: Dan Pate
Sponsors:
Thrivent Financial for Lutherans
All Saints Lutheran Church
Faith Lutheran Church
Grace Lutheran Church
Messiah Lutheran Church
St. Marks Lutheran Church
| DATE | DAY | ACTIVITY |
|---|---|---|
| 2/26/08 | Tu | Cut lumber & mark plates for wall construction in warehouse|
| 3/1/08 | Sa | Build walls in warehouse|
| 3/4/08 | Tu | Take shed to site & build shed (if pad ready)|
| 3/6/08 | Th | Install base plate & band; build & install support trusses|
| 3/8/08 | Sa | Install floor joists, deck floor system and waterproof floor|
| 3/18/08 | Tu | Take walls to site & complete floor system|
| 3/20/08 | Th | Layout floor for walls; add OSB & blueboard to end trusses|
| 3/22/08 | Sa | Erect walls; square walls; brace walls; put OSB on corners; erect trusses; roof sheathing|
| 3/25/08 | Tu | Complete roof sheathing; tar paper roof; install barge rafters & install bird boxes|
| 3/27/08 | Th | Install drip edge; install attic door & attic floor|
| 3/29/08 | Sa | Shingle roof & ridge; rough-in electrical; plumbing & HVAC; install external windows & doors|
| 4/1/08 | Tu | Complete 3/29/08 work; finish shed|
| 4/3/08 | Th | Layout starter strip & install corners for vinyl siding|
| 4/5/08 | Sa | Install vinyl siding; exterior & interior insulation; install vinyl siding on shed|
| 4/8/08 | Tu | Catch up day|
| 4/10/08 | Th | Catch up day|
| 4/12/08 | Sa | Install drywall & finish & blow ceiling (contract)|
| 4/15/08 | Tu | Install baseboard & door trim|
| 4/17/08 | Th | Complete baseboard & door trim|
| 4/19/08 | Sa | Paint walls & trim doors; begin landscaping; build porches|
| 4/22/08 | Tu | Prepare for tile (clean & mop floors)|
| 4/24/08 | Th | Install underlayment for tile & tile layout|
| 4/26/08 | Sa | Install tile; install & paint bifold doors|
| 4/29/08 | Tu | Install bathroom vinyl & strip|
| 5/1/08 | Th | Finish electrical, plumbing, HVAC|
| 5/3/08 | Sa | Start landscaping (flowers, etc)|
| 5/6/08 | Tu | Finish landscaping (spread grass seed & cover with straw|
| 5/8/08 | Th | Install storm doors|
| 5/10/08 | Sa | Install closet hardware & kitchen cabinets; Install window blinds|
| 5/13/08 | Tu | Catch up day|
| 5/15/08 | Th | Catch up day|
| 5/17/08 | Sa | Install bathroom accessories|
| 5/20/08 | Tu | Blow in attic insulation|
| 5/22/08 | Th | Mop & wax floors|
| 5/24/08 | Sa | Work punch list items|
| 5/31/08 | Sa | Dedication Ceremony