Volunteers inside a new home in progress.
6208 Melrose Dr

Family: Krystal Franklin
House Leader: Doug Seay
Sponsors:
Bicentennial Chapel
First Missionary Baptist Church
First United Methodist Church
Latham United Methodist Church
Mallard Creek Primitive Baptist Brotherhood Association
Scientific Atlanta

Date Day Job
2/26/08 Tu Mark plates; cut walls in warehouse
2/28/08 Th Mark plates; cut walls in warehouse
3/1/08 Sa build walls in warehouse
3/4/08 Tu build floor system
3/6/08 Th build floor system
3/8/08 Sa build floor system
3/11/08 Tu Prep floor system for walls
3/12/08 We Flooring joist inspection
3/13/08 Th Deliver walls to site
3/14/08 Fr Deliver roof trusses to site
3/15/08 Sa Rain; No work
3/17/08 Mo Mark floors for walls
3/18/08 Tu Erect, align & brace exterior walls, Deck walls w/OSB
3/20/08 Th Erect, align & brace ext. & int. walls, Deck walls w/OSB
3/21/08 Fr Good Friday
3/22/08 Sa Easter Weekend; No Work
3/25/08 Tu Erect, align & brace interior walls, Deck walls w/OSB
3/27/08 Th Erect, align & brace interior walls, Deck corners w/OSB, Deliver scaffolding to site
3/29/08 Sa WALL RAISING CELEBRATION Prep gable end trusses, Install vertical bracing for gable end trusses, Install nailing strips braces for end trusses, Mark cap plates for truss locations, Attach front/rear truss positioning line across rear of house, Erect roof trusses, Deck roof, Trim eaves
4/1/08 Tu Cover roof w/tar paper, Mount facia and drip edge
4/3/08 Th Mount facia & drip edge;Install barge rafters
4/5/08 Sa Build temp steps, front & back, Wrap house with Ty-Vek; Install windows, Install hurricane brackets, Install sheetrock blocking, Install exterior doors; start porches, Build sheds
4/7/08 Mo Install HVAC initial; plumbing rough in, Roof house; framing inspection
4/8/08 Tu Pull wire & rough electrical; build porches, Mount starter strip for vinyl siding, Install insulation baffles
4/9/08 We Mechanical, plumbing& electrical rough in inspection
4/10/08 Th Install insulation baffles, build porces, Deliver sheetrock
4/11/08 Fr Install sheetrock
4/12/08 Sa Build porches, install vinyl siding, Insulate under floors, Install vinyl siding in shed
4/14/08 Mo Install sheetrock
4/15/08 Tu Install sheetrock; install vinyl siding
5/10/08 Sa Start installation of vinyl flooring
5/13/08 Tu Install vinyl flooring
5/15/08 Th
5/17/08 Sa Install baseboard; install vinyl flooring, Start installation of baseboard, Install window sills
5/20/08 Tu Install baseboard; install cabinets
5/22/08 Th Install baseboard; install window sills
5/24/08 Sa Memorial Day; No work
5/27/08 Tu Install baseboard
5/29/08 Th Install baseboard
5/30/08 Fr Paint exterior doors
5/31/08 Sa Install kitchen cabinets, Install medicine chest & bath cabinets, Install bathroom towel racks, tp holder, Venetian blinds
6/2/08 Mo Paint exterior doors
6/3/08 Tu Install interior doors & hardware
6/5/08 Th Install interior doors & hardware
6/6/08 Fr Paint exterior doors
6/7/08 Sa Install shutters; install front door peep hole, Install closet shelves
6/9/08 Mo Paint exterior doors
6/10/08 Tu Touch up painting; punch list; final HVAC, Plumbing and electrical complete
6/12/08 Th Clean & prepare floors; punch list
6/13/08 Fr Final plumbing, elec. & mech.inspection
6/14/08 Sa Landscaping; punch list; install stove
6/17/08 Tu Touch-up painting; punch list
6/19/08 Th Touch-up painting; punch list
6/21/08 Sa Final clean up; clean house; wash windows, Clean & wax floors
6/24/08 Tu Touch-up painting; punch list
6/26/08 Th Punch list
6/27/08 Fr Happy Birthday Kyron!
6/28/08 Su House Dedication Ceremony