| Date | Day | Job |
|---|---|---|
| 2/26/08 | Tu | Mark plates; cut walls in warehouse |
| 2/28/08 | Th | Mark plates; cut walls in warehouse |
| 3/1/08 | Sa | build walls in warehouse |
| 3/4/08 | Tu | build floor system |
| 3/6/08 | Th | build floor system |
| 3/8/08 | Sa | build floor system |
| 3/11/08 | Tu | Prep floor system for walls |
| 3/12/08 | We | Flooring joist inspection |
| 3/13/08 | Th | Deliver walls to site |
| 3/14/08 | Fr | Deliver roof trusses to site |
| 3/15/08 | Sa | Rain; No work |
| 3/17/08 | Mo | Mark floors for walls |
| 3/18/08 | Tu | Erect, align & brace exterior walls, Deck walls w/OSB |
| 3/20/08 | Th | Erect, align & brace ext. & int. walls, Deck walls w/OSB |
| 3/21/08 | Fr | Good Friday |
| 3/22/08 | Sa | Easter Weekend; No Work |
| 3/25/08 | Tu | Erect, align & brace interior walls, Deck walls w/OSB |
| 3/27/08 | Th | Erect, align & brace interior walls, Deck corners w/OSB, Deliver scaffolding to site |
| 3/29/08 | Sa | WALL RAISING CELEBRATION Prep gable end trusses, Install vertical bracing for gable end trusses, Install nailing strips braces for end trusses, Mark cap plates for truss locations, Attach front/rear truss positioning line across rear of house, Erect roof trusses, Deck roof, Trim eaves |
| 4/1/08 | Tu | Cover roof w/tar paper, Mount facia and drip edge |
| 4/3/08 | Th | Mount facia & drip edge;Install barge rafters |
| 4/5/08 | Sa | Build temp steps, front & back, Wrap house with Ty-Vek; Install windows, Install hurricane brackets, Install sheetrock blocking, Install exterior doors; start porches, Build sheds |
| 4/7/08 | Mo | Install HVAC initial; plumbing rough in, Roof house; framing inspection |
| 4/8/08 | Tu | Pull wire & rough electrical; build porches, Mount starter strip for vinyl siding, Install insulation baffles |
| 4/9/08 | We | Mechanical, plumbing& electrical rough in inspection |
| 4/10/08 | Th | Install insulation baffles, build porces, Deliver sheetrock |
| 4/11/08 | Fr | Install sheetrock |
| 4/12/08 | Sa | Build porches, install vinyl siding, Insulate under floors, Install vinyl siding in shed |
| 4/14/08 | Mo | Install sheetrock |
| 4/15/08 | Tu | Install sheetrock; install vinyl siding |
| 5/10/08 | Sa | Start installation of vinyl flooring |
| 5/13/08 | Tu | Install vinyl flooring |
| 5/15/08 | Th | |
| 5/17/08 | Sa | Install baseboard; install vinyl flooring, Start installation of baseboard, Install window sills |
| 5/20/08 | Tu | Install baseboard; install cabinets |
| 5/22/08 | Th | Install baseboard; install window sills |
| 5/24/08 | Sa | Memorial Day; No work |
| 5/27/08 | Tu | Install baseboard |
| 5/29/08 | Th | Install baseboard |
| 5/30/08 | Fr | Paint exterior doors |
| 5/31/08 | Sa | Install kitchen cabinets, Install medicine chest & bath cabinets, Install bathroom towel racks, tp holder, Venetian blinds |
| 6/2/08 | Mo | Paint exterior doors |
| 6/3/08 | Tu | Install interior doors & hardware |
| 6/5/08 | Th | Install interior doors & hardware |
| 6/6/08 | Fr | Paint exterior doors |
| 6/7/08 | Sa | Install shutters; install front door peep hole, Install closet shelves |
| 6/9/08 | Mo | Paint exterior doors |
| 6/10/08 | Tu | Touch up painting; punch list; final HVAC, Plumbing and electrical complete |
| 6/12/08 | Th | Clean & prepare floors; punch list |
| 6/13/08 | Fr | Final plumbing, elec. & mech.inspection |
| 6/14/08 | Sa | Landscaping; punch list; install stove |
| 6/17/08 | Tu | Touch-up painting; punch list |
| 6/19/08 | Th | Touch-up painting; punch list |
| 6/21/08 | Sa | Final clean up; clean house; wash windows, Clean & wax floors |
| 6/24/08 | Tu | Touch-up painting; punch list |
| 6/26/08 | Th | Punch list |
| 6/27/08 | Fr | Happy Birthday Kyron! |
| 6/28/08 | Su | House Dedication Ceremony |