Family: Victoria Erskine
House Leader: TBD
Sponsors:Women Build Guild
| Date | Day | Job |
|---|---|---|
| 4/1/ | Tu | Clean and level crawl space |
| 4/3/ | Th | Cut wood and mark plates in warehouse |
| 4/5/ | Sa | Build Walls in warehouse |
| 4.21.08-05.02.08 | Mon - Fri | Install sub-floor; deliver walls; Prepare trusses; erect walls, erect trusses; apply blueboard to walls, deck roof, install windows, ext. doors, hurricane clips, and deadwood (CareAVanners) |
| 05.10.08-05.17.08 | Saturday Tu, Th, Sat | Kick off Ceremony Install wall and floor insulation, vinyl siding |
| 05.20.08-05.22.08 | Tu, Th | Install wall and floor insulation, (Sheet rock by sub), vinyl siding |
| 5/24/2008 | Sa | No Work: Memorial Day |
| 05.27.08-05.31.08 | Tu, Th, Sat | Install porch beams, barge rafters, facia, attic access & floor, plumbing, electrical, HVAC rough-in |
| 06.03.08-06.07.08 | Tu, Th, Sat | Paint walls, build porches, finish vinyl siding and shutters |
| 06.10.08-06.14.08 | Tu, Th, Sat | Begin landscaping, install underlayment, floor covering |
| 06.17.08-06.21.08 | Tu, Th, Sat | Install & paint interior doors and trim, install cabinets, plumbing and electrical |
| 06.24.08-06.28.08 | Tu, Th, Sat | Install closet hardware, window blinds, storm doors, bathroom accessories, touch up paint, landscape |
| 07.01.08-07.03.08 | Tu, Th, Sat | Work punch list, blow attic insulation |
| 7/5/2008 | Sat | No work; July 4th weekend |
| 7/12/2008 | Sat | Dedication Ceremony |