6212 Melrose Dr

Family: Victoria Erskine
House Leader: TBD
Sponsors:Women Build Guild

Date Day Job
4/1/ Tu Clean and level crawl space
4/3/ Th Cut wood and mark plates in warehouse
4/5/ Sa Build Walls in warehouse
4.21.08-05.02.08 Mon - Fri Install sub-floor; deliver walls; Prepare trusses; erect walls, erect trusses; apply blueboard to walls, deck roof, install windows, ext. doors, hurricane clips, and deadwood (CareAVanners)
05.10.08-05.17.08 Saturday
Tu, Th, Sat
Kick off Ceremony
Install wall and floor insulation, vinyl siding
05.20.08-05.22.08 Tu, Th Install wall and floor insulation, (Sheet rock by sub), vinyl siding
5/24/2008 Sa No Work: Memorial Day
05.27.08-05.31.08 Tu, Th, Sat Install porch beams, barge rafters, facia, attic access & floor, plumbing, electrical, HVAC rough-in
06.03.08-06.07.08 Tu, Th, Sat Paint walls, build porches, finish vinyl siding and shutters
06.10.08-06.14.08 Tu, Th, Sat Begin landscaping, install underlayment, floor covering
06.17.08-06.21.08 Tu, Th, Sat Install & paint interior doors and trim, install cabinets, plumbing and electrical
06.24.08-06.28.08 Tu, Th, Sat Install closet hardware, window blinds, storm doors, bathroom accessories, touch up paint, landscape
07.01.08-07.03.08 Tu, Th, Sat Work punch list, blow attic insulation
7/5/2008 Sat No work; July 4th weekend
7/12/2008 Sat Dedication Ceremony