Family: Natasha Whitman
House Leader: Andy Trice
Sponsor: Trinity United Methodist Church
| DATE | DAY | ACTIVITY |
|---|---|---|
| 1/27/08 | Su | Cut wood and build headers and ladders; Organize for wall construction |
| 2/5/08 | Tu | Assemble wall sets (9AM-11:30AM) |
| 2/9/08 | Sa | Build Walls in warehouse (8AM-12PM) |
| 2/29/08 | Fr | Transport walls to construction site (8:30-11AM) |
| 3/1/08 | Sa | Wall raising Ceremony; Erect walls adn set roof trusses |
| 3/4/08 | Tu | Attach roof decking and fascia |
| 3/5/08 | We | Attach felt and drip edge to roof, wrap house in Tyvek Begin window and exterior door installation |
| 3/6/08 | Th | Finish window and exterior door installation and attach starter strips for vinyl siding |
| 3/8/08 | Sa | Attach vinyl siding, hurricane ties, deadwood, continue rough electrical installation, and attic floor and access |
| 3/11/08 | Tu | Build bird boxes adn frame porch |
| 3/12/08 | We | Finish bird boxes and porch frame |
| 3/13/08 | Th | Install deadwood, blocking and insulation baffles |
| 3/15/08 | Sa | Finish vinyl siding, install insulation and baffles |
| 3/18/08 | Tu | Final preparation for dry wall |
| 3/20/08 | Th | Build porch fake beams and complete unfinished projects |
| 3/22/08 | Sa | Easter Weekend; No work |
| 3/25/08 | Tu | No work scheduled |
| 3/27/08 | Th | Clean house after drywall installation |
| 3/29/08 | Sa | Prime and paint walls |
| 4/1/08 | Tu | Install interior doors |
| 4/3/08 | Th | Prepare floors for tile installation |
| 4/5/08 | Sa | Install vinyl tile |
| 4/8/08 | Tu | Begin interior trim installation |
| 4/9/08 | We | Kitchen cabinets, bath vanity and accessories |
| 4/10/08 | Th | Finish window and floor trim installation Electrical fixtures; access panel for tub |
| 4/12/08 | Sa | Install range hood |
| 4/15/08 | Tu | Install closet bifolds and closet hardware |
| 4/16/08 | We | Paint trim, exterior and interior doors; landscaping |
| 4/19/08 | Sa | Landscape yard, install shutters and mailbox |
| 4/22/08 | Tu | Develop punch list |
| 4/23/08 | We | Paint interior doors and trim, touch up walls as required Install window blinds |
| 4/24/08 | Th | Work punch list |
| 4/26/08 | Sa | Final landscaping and complete punch list |
| 4/29/2008 - 5/12/2008 | Tu thru Mon | Accomodation for schedule changes |
| TBD | Adopt-A-Room |